Answer: Eight hours (One day) Explanation: This timeframe includes measuring, cutting and assembling the pipe, securing the line, performing pressure tests, and ensuring everything meets code and safety standards. |
| Rough-In Plumbing Solutions, LLC |
Answer: Not sure Explanation: Well, it depends on a number of things. Does it include removal of old piping, or prep work? Is it a flanged connection, Or is there a tie-in? Is there offsets or rolling offsets? Am I working alone? Is the system under pressure? Providing a timeframe without knowing these things would be guess at best, and not accurate. |
| Parsons specialty welding |
Answer: Not sure Explanation: Every job is different . Can not estimate without a visual inspection. |
| Liquid Tech Plumbing & Heating inc. |
|
| ProMatcher |
Answer: Two to four hours Explanation: There is not enough info to correctly say. Is the gas line sized correctly? Is there walls or drywall removal included? Is there an existing gas pipe? Is there block walls or obstacles in the same location? In the wall or exposed hanging or mounted to wall? |
| Code Blue Plumbing |
Answer: One to two hours Explanation: All sections of pipe to be measured, cut, threaded and hung with a necessary shut-off valve. If proper sizing allows, an installer can easily get the required volume of gas from a branch line close to another appliance by disassembly of the drop to that appliance at the union. If cutting into an existing line is necessary, the job could take to the latter part of the estimated time frame. Turning the gas back on, leak checking, leak testing with pressure test, and lighting pilots on all the appliances should all be done within two hours without rushing through it. The time frame of two hours does not include inspection appointments. So the gas line, although installed in this time frame, cannot be used until inspected. |
| Hit the Gas LLC |
Answer: Two to four hours Explanation: Prof |
| Peace of Mind Plumbing LLC |
|
| ProMatcher |
Answer: One to two hours Explanation: It all depends on if the area is open and if there is anything in the way. |
| JD all service plumbing |
Answer: One to two hours Explanation: Most occasions this process is done in all steel piping. |
| Western Piping & Supply |
Answer: Four to six hours Explanation: It takes typically 4-6 hours to do it with the copper Lines and the testing for leaks. |
| All City Construction |
|
| ProMatcher |
Answer: Two to four hours Explanation: Maybe less time to install depending on circumstances at the job site such as personal storage or other obstructions. |
| East Coast Home Inspections LLC |